Orlando Utilities Commission (OUC) St. Cloud-Magnolia 230kV line (TA21-18): For the construction and operation of an approximately 21 mile long transmission line between the St. Cloud East substation in Osceola County and the Magnolia Ranch substation in Orange County. This application is being processed under the Florida Electric Transmission Line Siting Act.
DEP Siting Coordination Case Managers: Ann Seiler 850-717-9113 and Nate Senn 850-717-9111.
Relevant Project Information
- Public Service Commission (Docket# 20200107)
- Division of Administrative Hearings (Docket# 21-001939)
- Applicant
Project Filings
- Application (filed 6/11/2021)
Amendment to Application (filed 6/16/2021 - Complete Application) - Schedule (Order issued 6/25/2021 - revised schedule below approved 8/4/2021)
- OUC Newspaper Notices of Filing Application (published 6/30/2021 and 7/8/2021)
- DEP Florida Administrative Register - Notice of Receipt of Application (Published 7/1/2021 - go to page 16)
- DEP Determination of Completeness - found Incomplete (filed 7/19/2021)
- OUC's Direct Notice to Landowners (sent to DEP on 7/21/2021)
- Orange County Notice of Informational Public Meeting (published on 7/25/2021)
- OUC Newspaper Notices republished - Filing of Application (published on 7/28/2021 and 7/29/2021)
- OUC Completeness Response (filed 8/2/2021)
- Revised Schedule (8/4/2021 - ALJ approved - begins on page 13)
- OUC Revised Completeness Response (filed 8/12/2021)
- DEP Determination of Completeness (found complete 8/23/2021)
- Agency Reports (filed 9/9/2021)
- DEP Florida Administrative Register - Notice of Certification Hearing (Published 10/1/2021 - go to page 27)
- DEP Project Analysis Report (filed 10/4/2021)
- ALJ Order of Relinquishing and Closing Case (filed on 11/9/2021)
- OUC Notice of Cancellation of Certification Hearing (submitted 11/29/2021)
- DEP Florida Administrative Register - Notice of Cancellation of Certification Hearing (published on 11/30/2021) - go to page 15)
- Final Order Approving Certification (DEP issued 12/13/2021)