Manatee Power Plant

General Information

Title Information
Licensee Florida Power & Light Company
Certification # PA 02-44
Date Certified 04/14/2003
Description The site certification includes a 4-on-1 combined cycle unit (Unit 3) comprised of four nominal 170 MW combustion turbines with associated heat recovery generators and a nominal 470 MW steam turbine-electric generator, and associated support facilities.
Fuel Type Natural Gas
Nominal Rating 1,150 MW
Address/Location 19050 Sate Road 62
Parrish, FL 34219
County Manatee
Districts Florida Department of Environmental Protection Southwest District
Southwest Florida Water Management District


Facility State Documents

Facility Documents Description
Conditions of Certification Facility License
Post-Certification Submittal Summary Summary of Submittals required by Conditions
Modifications Final orders Modifying the Conditions
Amendments Amendment Approval Letters
Final Order(s) Original Final Order of Certification and, if applicable, Land Use Consistency
Site Certification Application Original and Supplemental Application(s)


Department Permits under Federal Programs

Program Type Facility ID #
Air Construction and Operation 0810010 *
Water NPDES 0032174 *

(*copy the id # and paste into the Facility ID field to locate associated Permits)