Seminole Electric Cooperative, Inc. and JEA Keystone-Firestone Line

General Information

Title Information
Licensee Seminole Electric Cooperative, Inc (SECI) and JEA
Certification #                                     TA 90-08
Date Certified 06/12/1991
Description This transmission line begins at SECI's Seminole Generating Station and connects to Clay Electric Cooperative's Riverview, Florahome, Keystone and Black Creek Substations, ending at the JEA's Firestone Substation.
Line Length 70 Miles
Voltage 230 kV
Counties Crossed: Putnam and Duval
Districts Florida Department of Environmental Protection Northeast District
St. Johns River Water Management District


Facility State Documents

Facility Document(s) Description
Conditions of Certification Facility License
Post-Certification Submittal Summary Summary of Submittals Required by Conditions
Modifications Final Orders Modifying the Conditions
Amendments  Amendment Approval Letters
Final Order Original Final Order of Certification
Site Certification Application * Original and Supplemental Facility Application(s)

* Please note that this link goes to the OCULUS logon page - click on PUBLIC OCULUS LOGIN to view the application sections

Last Modified:
October 11, 2024 - 1:42pm

Some content on this site is saved in an alternative format. The following icons link to free Reader/Viewer software:
PDF: | Word: | Excel: